Timeline

Month Fellowship Activities
August 2013 Establishment and refinement of fellowship:

  • Develop detailed management plan
  • Develop communication strategy including records, meetings, repositories, reporting etc.
  • Convene reference group
  • Confirm external evaluator and develop evaluation framework

Work with Business Development Team 1

September 2013 Work with Business Development Team 2

Work with Business Development Team 3

Review cycle 1

October 2013 Develop web resources/good practice examples

Work with Business Development Team 1

November 2013 Work with Business Development Team 2

Work with Business Development Team 3

Review cycle 2

December 2013 Further develop web resources/good practice examples

Work with Business Development Team 1

January 2014 Work with Business Development Team 2

Work with Business Development Team 3

Review cycle 3

Convene reference group

Interim Report

February 2014 Further develop web resources/good practice examples

Work with Business Development Team 1

March 2014 Work with Business Development Team 2

Work with Business Development Team 3

Review cycle 4

April 2014 Further develop web resources/good practice examples

Work with Business Development Team 1

May 2014 Work with Business Development Team 2

Work with Business Development Team 3

Review cycle 5

Further develop web resources/good practice examples

Convene reference group

Dissemination workshops (Sydney, Melbourne) to showcase and disseminate the strategic paper and resources

June 2014 Dissemination workshops (Brisbane, Adelaide, Perth) to showcase and disseminate the strategic paper and resources
July 2014 Prepare Final Report

Presentation of Findings: ABDC T&L Network

Evaluation report by external evaluator.

Final report submitted to OLT and Reference Group

August 2014 Finalise